    Hi everyone
    I'm testing the PO generator process in GP and I noticed that it automatically removes the selection of "calculate MRP for this item/site" when you change the Order policy in the Item Resource Planning Maintenance window.

    We are currently using "period order quantity" as the order policy which enables MRP. For visibility we use the .MRP Workbench window and it allows us to see all of the ins and outs for each item by location and by days, weeks or months.

    My question would be.... once I switch the order policy to "USE PO GEN" is there another window/view that would replace .MRP Workbench that would still allow us to see the same information broken down by location as well as by day, week or month?

    thank you in advance for your help

    ------------------------------