All,
I have a customer that wants to use Machine Costs on their Routers where the Machine Cost is setup as a Per Hour Rate. On the Router we have 1 Step which only has Machine Time of .5 (for costing) and Queue Time of .5 (for scheduling). The default setup in GP takes the Machine Time and multiplies it by the Number of Pieces on the MO. I want to update the SP that does this calculation to calculate the Machine Cost as .5 Machine Hours x Machine Hourly Rate and disregard the number of pieces being produced.
Does anyone know what sp is calculating the MO Costs which when an MO is Released populate the MO Variance window (table WO010032), I suspect that I'll also need to update whatever sp is grabbing costs for potential WIP and most importantly Receiving and Closing. The Machine Costs are set to Backflush.
Yes I know I can use the Setup Labor bucket but the client wants the cost to be in the correct bucket on the MO Variance window (Machine) so using the Setup Labor bucket/coding isn't ideal but I do realize that will work so more importantly I'm looking for the sp's or another resolution that will do the Math for Machine Costs based on the Routing Step Machine Hours x Machine Hourly Rate and if the Machine is setup to use Per Piece Cost to then calculate Machine Costs as Nbr of Pieces x Machine Per Piece Cost.
Any guidance is greatly appreciated.
------------------------------
Wally Dodds
Dorado Solutions
West Chester PA
------------------------------